Oracle Application Implementation Methodology

Oracle Application Implementation Methodology

To achieve a successful implementation of Oracle Applications a number of methodologies have been formulated. These are driven by industry case studies and past experiences. Many of them are based on the rich user experiences shared in various user groups and special interest groups. Among them Oracle's Application Implementation Methodology is one of most mature and 
proven one. Although AIM is not the only approach vouched by Oracle. It also has a Oracle Fast Forward approach which  focuses on rapid implementation of Oracle Applications. During one my recent projects i had a chance to work with the  Application Implementation Methodology approach, and i must say at the end of the day i was pleasantly surprised.

The Oracle Application Implementation Methodology (AIM) is a proven approach for implementation Oracle Applications across  business domains. This approach has been developed by oracle in constant collaboration within its partner network.

According to oracle "AIM provides the tools needed to effectively and efficiently plan, conduct, and control project steps to successfully implement new business systems."

The AIM is delivered in the form of a software bundle that packages the various document templates which have been identified as deliverables under the AIM approach. These are in the form of easily editable Microsoft documents like word, excel and mpp documents.

The Software is currently available only to Oracle Partners through the Oracle Partner Network (OPN).The software installation itself is quite simple and gets running within a few clicks.
The software presents a graphical user interface running within a web browser allowing you to browse though the various  deliverables.

Although most of the deliverables are focused on the functional domain areas. There also quite a few deliverables for  the Oracle Applications DBA /Technical Architect which have been identified in AIM.In my current post i will be focusing on these deliverables only.

The AIM approach has been divided in the various phases, which are

  • Definition
  • Operational Analysis
  • Solution Design
  • Build
  • Transition
  • Production

Below i will discuss the deliverables required under each of these phases from the Applications DBA/ TA .

Definition

The main deliverables that are defined under this stage are

TA.010 Define Architecture Requirements and Strategy
The focus of this document would be to provide the technical architecture and strategy that will be implemented to achieve a  successful implementation of the project.

TA.020 Identify Current Technical Architecture
The scope of this document included to understand and identify the existing application. interfaces networks and hardware  configurations.

TA.030 Develop Preliminary Conceptual Architecture
The objective of this task is to develop a conceptual architecture that will best fit the business objets taking into consideration the project constraints.

Operations Analysis
The main deliverables that are defined under this stage are

TA.050 Define System Availability Strategy
The focus of this document/task is to identify a system availability strategy for business. in case business require high  availability a strategy should be specified here to address it.

TA.070 Revise Conceptual Architecture
Under this task you revise the conceptual architecture you delivered as part of your TA. 30 to incorporate new requirements or findings.

Solution Design
The main deliverables that are defined under this stage are

TA.080 Define Application Security Architecture
The objective of this document is to incorporate application and database level security requirements in your architecture that have been identified by the business.

Build
The main deliverables that are defined under this stage are

TA.090 Define Application and Database Server Architecture
In task you design the new logical and physical architectures for the database tier and the application server tier, which has been conceptual so far.

TA.100 Define and Propose Architecture Subsystems
This document should focus on the requirements for additional components which may not have been a part of the initial plan.

TA.110 Define System Capacity Plan
Under this document you define the capacity plan for your system bearing in line with the business growth.

TA.120 Define Platform and Network Architecture
This document takes care of your Operating system and network architecture of your system.

TA.130 Define Application Deployment Plan
This document covers the deployment plan and installation of your application as according to the defined architecture.

TA.140 Assess Performance Risks
This document should cover the potential risk to your applications and ways to mitigate them.

TA.150 Define System Management Procedures
The scope of this document includes to cover the procedures maintenance of the application .

Transition
The transition phase does not have any deliverable particular to the DBA/TA.

Production
The main deliverables that are defined under this stage are

PM.140 Propose Future Technical Direction
The focus of this document is to identify innovations and software enhancements with respect to performance efficiency and functionality. Ideally the project manager and the DBA would work in collaboration to deliver this document.

While concluding the post i will like to reiterate that the scope of AIM approach is much more than what has been described in this post. The main aim has been to concentrating on the DBA/TA deliverables within AIM.

TrackBack

TrackBack URL for this entry:
http://www.appsdbablog.com/blog-mt/mt-tb.fcgi/35

Comments

Very Good Information, so you cannot get AIM from OTN or the edelivery?

Remy

Thank you Remmy,
As of now i dont know any link in OTN or edelivery for AIM.
Sam

this is the only spot I've ever seen it on: http://download-east.oracle.com/partners/265498.EXE

Of course, this isn't free software.

Yeah not a free software,
nevertheless freely downloadable from the link you sent :)

Sam

i need RD20,BP80 sample for project ( not empty) for finacail module

query for instalation of oracle apps financial 11i

iwant all documents of aim.

Post a comment

(If you haven't left a comment here before, you may need to be approved by the site owner before your comment will appear. Until then, it won't appear on the entry. Thanks for waiting.)